A PRE-CONSTRUCTION CHECKLIST FOR OWNER-BUILDERS

Author: John Stubstad, a construction consultant with 20 years experience helping owner-builders. John’s firm is Owner Build Homes, www.owner-build.com.

Purpose of the checklist: This will guide an owner-builder through the pre-construction stage. It may also help someone decide whether to be an owner-builder. By reading the list one can get an idea of a project’s size and a feel for whether he/she is up to the task.

Who should be an owner-builder? If you have some time and a strong desire to build, you should be able to handle it. If you are short on experience or financing you can probably still do it but you may need a consultant or a package supplier to help you.

Limitations of the checklist: (attorney required disclosures) (1) This checklist is not guaranteed to be complete or free of errors. If you suffer from reliance on it, you agree not to sue the author or his firm. After all, you are not paying for it. (2) Some steps will not apply to your situation. If you are not using an owner-builder consultant, for example, you can ignore references to one.

        PRE-CONSTRUCTION CHECKLIST

#     CRITICAL STEPS         NON-CRITICAL STEPS
1     Select building lot and put it in escrow
2     Select a home plan or sketch one yourself
3                     Give a copy of plan to your owner-builder consultant if you have one
4     Your consultant gauges construction cost and availability of financing
5                     Ask Building Dept if lot is buildable
6                     Ask Building Dept if soil report is needed for footings
7                     Ask Building Dept if soil compaction test is needed for slab
8     Sign agreement with your consultant if you plan to use one
9                     Buy Building Dept’s owner/builder book if they have one
10                   Ask Health Dept if the lot needs a perc test
11                    If lot is on septic, buy Health Dept's septic guidelines manual
12                   Ask friends and neighbors for names of good subcontractors
13    Consultant secures preliminary, non-binding approval from lender
14                   If a soils report is needed, find a soils engineer
15                   Ask soils engineer for soil test letter if required
16                   Stake house corners on lot
17                   Sketch site plan and give to drafter or ask drafter to draw one
18                   Obtain perc test if needed
19                   Request sewer hookup if lot is on sewer
20                   If not, draw leach line layout and give to drafter or ask drafter to draw one
21    Drafter prepares preliminary design
22                   Consultant provides pre-construction schedule and list of needed trades
23    Review preliminary design
 

#      CRITICAL STEPS         NON-CRITICAL STEPS

24                   Ask consultant to review preliminary design also

25                   Ask excavator if you need a grading permit and grading plan
26                   Ask Building Dept if you need a civil engineer for grading plan
27                   Ask Building Dept for cost of permits
28    Ask drafter to revise preliminary design
29                   Take perc test and leach line layout and apply for septic permit if needed
30    Obtain preliminary design from drafter, review and approve it
31                   Ask drafter to print two sets of preliminary design
32                   Give one set to consultant for review
33                   Ask drafter or civil engineer to draw grading plan if needed
34    Drafter prepares floor plans and elevations
35    Review floor plans and elevations
36                   Pick up grading plan if needed
37                   Take grading plan to Building Dept and apply for grading permit if needed
38    Ask drafter to revise floor plans and elevations
39    Approve floor plans and elevations
40                   Ask drafter to print two sets of floor plans and elevations
41                   Give one set to consultant for review
42                   Ask drafter or consultant for energy usage compliance reviewer if required
43                   Ask drafter if structural engineer is needed
44                   If one is needed, locate structural engineer
45                   Call utilities and ask for their lead times
46                   Order power, water, phone and cable
47                   Ask Postal Service for address
48    Drafter prepares architectural drawings
49    Review architectural drawings
50                   Ask drafter to print 4 sets of preliminary architectural drawings
51                   Give out two of the sets to subs, one set per sub
52                   Commit subs on when they will return drawings
53                   Give one set to consultant for review
54                   Check on progress of grading permit if an application was filed
55    Drafter revises architectural drawings
56    Approve architectural drawings
57                   Check on progress of septic permit if an application was filed
58    Ask drafter to print 4 sets of owner-approved architectural drawings
59    Slack time
60                   Give a set to energy compliance reviewer if needed
61                   Give a set to structural engineer if engineering needed
62                   Give a set to consultant
63                   Give grading plan corrections to whoever drew the grading plan
64                   Give septic corrections to drafter
65                   Ask foundation sub to look at lot and foundation plan
66                   Give out any extra sets of plans to subs for bids
67                   Drafter or civil engineer corrects grading plan
 

#      CRITICAL STEPS         NON-CRITICAL STEPS

68                   Drafter corrects septic plan

69    Structural engineer prepares structural calcs if one was hired
70                   Energy compliance reviewer does energy calcs if one was hired
71                   Consultant obtains truss calcs if plans call for trusses
72    Give structural engineer’s calcs to drafter
73                   Give energy compliance reviewer’s calcs to drafter
74                   Ask excavator to review grading plan
75                   Ask consultant for budget form
76                   Enter cost of permits, drafting, engineering and land on budget
77                   Shop for construction insurance
78    Drafter uses structural calcs to finish structural drawings
79                   Consultant gives truss calcs to owner to pass on to drafter
80    Ask drafter to print 6 sets of working drawings including structural pages
81                   Check on progress of grading and septic permits if they were requested
82    Submit 3 complete sets of plans including engineering and truss calcs to Bldg Dept
83                   Building Dept accepts plans for plan check
84    Give complete sets of drawings to subs who need complete sets to bid
85                   Collect bids and earlier sets of plans from subs
86                   Recycle plans to more subs for more bids
87                   Find out amount of school, park and fire fees
88                   Enter fees and misc costs on construction budget
89                   Health Dept approves septic permit if application was filed
90                   Building Dept approves grading permit if application was filed
91                   Building Dept does plan check and lists corrections
92                   Call Building Dept to see if corrections are ready
93                   Pick up plan check corrections when they are ready
94                   Pick up approved leach line layout when it is ready
95                   Pick up approved grading plan when it is ready
96    Collect enough bids for a budget
97                   Give plan corrections and approved grading and leach plans to drafter
98    Fill in construction budget
99                   Drafter corrects working drawings
100                 Ask drafter to print corrected plans for Building Dept
101                  Obtain bids on grading work
102   Send budget to consultant for review
103                  Ask consultant for a construction schedule for after ground breaking
104                  Pick up corrected plans from drafter
105                  Do not start grading before loan closes
106                  Give corrected plans to Building Dept
107                  Consultant advises which jobs need more or better bids
108   Complete the application for construction loan – give to consultant
109                  Consultant provides part 2 of construction schedule
110                  Collect 3 bids for each major job
111                  Ask suppliers to recommend additional installers for jobs without 3 bids
 

 #     CRITICAL STEPS         NON-CRITICAL STEPS

112                  Select subs for first half of job – through locking of house
113                  Schedule a start date for each of these subs
114                  Tell subs of their selection and scheduled start date
115                  Confirm they will be available to start on that date
116                  Ask subs how long they will need to finish job
117                  Building Dept clears all corrections and approves house plans
118                  Pick up final, approved plans from Building Dept
119                  Ask drafter to print 4 sets of copies of final plans
120                  Pick up 4 copies - keep original and one copy
121                  Sign one copy to signify final customer approval
122                  Give 3 sets to consultant including signed copy
123                  Inform lender of Building Dept approval
124   Lender gives final approval of construction loan
125                  Ask consultant for first load lumber list
126                  Put subs' time estimates on part 2 of construction schedule
127                  Add something like 20% to their estimates
128                  Revise schedule based on latest time estimates from subs
129                  Advise subs of their revised start dates
130   Lender closes construction loan
131   Start grading